Let´s click inside the field called “If”:.Name it as “Incremento productividad 50% Ingenieros” within the field “Global Change Name”.Select “Activity Resource Assignments” withing the field “Select Subject Area”.This is the same as multiplying your Remaining Units / Time by 2.
Let´s apply what we have seen so far in the following example: we have seen that both the performance of Mechanical Engineers and Finishing Engineers is greater than initially planned, they are capable of doing twice as much work in the same period of time, respectively. “Then”: “then” adjust the main parameters.To do this, you must first know what each of the fields that are shown mean: “If”, “Then”, “Else”. Start to create the command to make the change.We will quickly see the meaning of the different fields in the window called “Modify Global Change”:.They can be enabled so that all the users, another user or the current user have access to. In the window that has been opened, the different Global Change that you have created are shown.You are in now! Let´s create our first Global Change as follows: It’s simple and you just have to follow this path in your toolbar: Tools / Global Change, or select the icon. Let’s start by launching the Global Change tool window.
Well, yes, there is! The solution to your problems is in the Global Change Tool that Primavera P6 Professional provides, giving you the opportunity to create and parameterize almost any change that goes through your mind, and thus reduce to seconds what up to now has supposed hours of work.
You have even come to ask if there could be another faster way to carry out your schedule update work or simply make changes in activities, expenses or allocation of resources. “I’m sure there must be a faster way to match the Remaining Units to the Budgeted Labor Units of a certain section of my project,” “It’s taking me hours to copy the original Activity IDs of my schedule into a new text column”, “I wish there was a way to make the Remaining Cost of the construction activities double”, “I’ll be home late, I have to update my program manually, activity by activity”.įor sure the scenarios of the previous paragraph are familiar. If you are looking for a quality leap in your skills as a planner with Primavera P6 Professional and improving your daily efficiency as a scheduler, this article about P6 Global Change tool will show you the way.